日前(qian),華騰(teng)新材廣東國(guo)望公司20000噸(dun)/年功能(neng)性(xing)聚氨酯粘接材料自動化生產建設項(xiang)(xiang)目(即“退城(cheng)入(ru)園”項(xiang)(xiang)目)主(zhu)體(ti)建筑砌(qi)體(ti)已全部(bu)完成,現已進入(ru)室內裝(zhuang)修及(ji)外墻安(an)裝(zhuang)階(jie)段(duan),室外工程即將同時進行(xing)施工。

隨著首批主體設(she)備運(yun)輸到場(chang),土建施(shi)(shi)工(gong)(gong)(gong)(gong)及(ji)工(gong)(gong)(gong)(gong)藝安(an)裝處(chu)于(yu)交叉作(zuo)業(ye)(ye)階(jie)段(duan),存(cun)在著工(gong)(gong)(gong)(gong)作(zuo)面大,內(nei)容復(fu)雜的(de)情(qing)況(kuang)。為保證(zheng)施(shi)(shi)工(gong)(gong)(gong)(gong)安(an)全和工(gong)(gong)(gong)(gong)作(zuo)效率(lv),項目小組多次組織召開施(shi)(shi)工(gong)(gong)(gong)(gong)單位協調調度(du)會,對(dui)交叉作(zuo)業(ye)(ye)面、場(chang)地移交、預埋件及(ji)預留(liu)孔(kong)留(liu)置(zhi)等問題進(jin)行(xing)技術溝通(tong)和梳理(li),做足前期準(zhun)備和協調安(an)排,有效防(fang)止了施(shi)(shi)工(gong)(gong)(gong)(gong)單位作(zuo)業(ye)(ye)重疊(die)、效率(lv)降低、推諉扯皮等情(qing)況(kuang)的(de)發生,保證(zheng)了工(gong)(gong)(gong)(gong)程(cheng)進(jin)度(du)如期進(jin)行(xing)。

7月份以來,項(xiang)目所在的廣東地區酷熱高溫,項(xiang)目小組成員(yuan)不畏酷暑(shu),常駐現場,對(dui)技術難點及時反(fan)應,狠抓(zhua)落實,齊心(xin)協力趕工期(qi)搶進度(du)。同(tong)時,國望公司老(lao)廠區設(she)備轉移停(ting)產前的生(sheng)產備貨也如(ru)火如(ru)荼進行,公司全體員(yuan)工鉚足干勁,齊心(xin)協力助力工程建設(she)。